January 21, 2026 1:57 pm

GAIL Expressway Gas Pipeline and the Future of Integrated Corridors

CURRENT AFFAIRS: GAIL (India) Ltd, PM GatiShakti, Samruddhi Mahamarg, Mumbai–Nagpur Natural Gas Pipeline, utility corridor, MSRDC, horizontal directional drilling, city gas distribution, clean energy transition

GAIL Expressway Gas Pipeline and the Future of Integrated Corridors

A milestone in corridor-based infrastructure

GAIL Expressway Gas Pipeline and the Future of Integrated Corridors: India has marked a significant infrastructure achievement with the completion of the 694-km Mumbai–Nagpur Natural Gas Pipeline by GAIL (India) Ltd.
The project demonstrates how transport infrastructure can simultaneously function as a utility corridor under integrated planning.

The pipeline has been laid almost entirely within a 3-metre-wide strip along Maharashtra’s Samruddhi Mahamarg, setting a precedent for space-efficient infrastructure development.

PM GatiShakti in action

The project is widely viewed as a practical success of the PM GatiShakti framework.
This approach focuses on synchronised planning across sectors to avoid duplication, delays, and land acquisition conflicts.

By aligning pipeline construction with expressway development, the project reduced costs, environmental impact, and right-of-way disputes.
Static GK fact: PM GatiShakti was launched in 2021 to integrate infrastructure planning across 16 central ministries using a GIS-based platform.

Engineering within extreme constraints

Nearly 96% of the pipeline length runs within the narrow expressway utility strip.
Conventional gas pipelines usually require 20–30 metres of working width, making this project a major engineering departure.

A 24-inch high-capacity steel pipeline was installed within space comparable to a pedestrian footpath.
This constraint influenced welding techniques, construction sequencing, safety buffers, and equipment selection.

Tackling the Western Ghats challenge

The most complex section lay in the Western Ghats near Fugale hill, where elevation differences exceeded 200 metres.
The terrain involved hard rock, steep gradients, dense vegetation, and intense monsoon rainfall.

Engineers deployed a hybrid method combining horizontal directional drilling with a thruster-based pulling system.
Nearly one kilometre of pipeline was pulled through difficult terrain, showcasing advanced construction capability.

Static GK Tip: Horizontal directional drilling is commonly used to cross rivers, highways, and eco-sensitive zones without surface disruption.

Coordination and regulatory execution

Although the project received initial approval in May 2020, progress was slowed by the pandemic and forest clearances.
Clearances across 10 districts, covering about 56 km, were obtained only in April 2023.

GAIL adjusted work schedules and coordinated daily with 16 expressway packages and multiple pipeline sections.
The collaboration with Maharashtra State Road Development Corporation is now viewed as a model for future corridor-based projects.

Energy and economic significance

The pipeline has a capacity of 16.5 million standard cubic metres per day with bi-directional flow capability.
It will support city gas distribution in 16 districts of Maharashtra.

The network is expected to supply piped natural gas to nearly 95 lakh households and fuel over 1,700 CNG stations.
Sectors such as fertilisers, power, chemicals, and MSMEs along the expressway corridor stand to benefit significantly.

Static GK fact: Natural gas emits lower particulate matter and carbon dioxide compared to coal and petroleum-based fuels.

A replicable infrastructure blueprint

The project establishes a new template for integrating pipelines, highways, and future utilities.
Such multi-utility corridors can accelerate project delivery while conserving land and reducing environmental impact.

This model aligns infrastructure expansion with India’s clean energy transition and logistics modernisation goals.

Static Usthadian Current Affairs Table

GAIL Expressway Gas Pipeline and the Future of Integrated Corridors:

Topic Detail
Project name Mumbai–Nagpur Natural Gas Pipeline
Executing agency GAIL (India) Ltd
Total length 694 kilometres
Corridor width 3 metres
Associated expressway Samruddhi Mahamarg
Pipeline capacity 16.5 MMSCMD
Key framework PM GatiShakti
Strategic impact Integrated transport and energy corridor
GAIL Expressway Gas Pipeline and the Future of Integrated Corridors
  1. GAIL completed 694-km Mumbai–Nagpur gas pipeline
  2. Pipeline laid along Samruddhi Mahamarg expressway corridor.
  3. Project demonstrates utility corridor integration with highways.
  4. Nearly entire pipeline fits within 3-metre-wide strip.
  5. Conventional pipelines require 20–30 metres working width.
  6. Project showcases PM GatiShakti integrated planning success.
  7. PM GatiShakti launched in 2021 using GIS platform.
  8. Alignment reduced land acquisition and environmental costs.
  9. 96% pipeline length lies within expressway utility zone.
  10. A 24-inch high-capacity steel pipeline was installed.
  11. Western Ghats section faced 200-metre elevation challenges.
  12. Engineers used horizontal directional drilling techniques.
  13. Thruster-based pulling system aided difficult terrain crossing.
  14. Forest clearances across 10 districts delayed project.
  15. Pipeline capacity stands at 5 MMSCMD bi-directional flow.
  16. Project supports city gas distribution in 16 districts.
  17. Nearly 95 lakh households will receive piped gas.
  18. Over 1,700 CNG stations will benefit from supply.
  19. Collaboration with MSRDC seen as model approach.
  20. Project sets blueprint for multi-utility infrastructure corridors.

Q1. Which organisation executed the Mumbai–Nagpur Natural Gas Pipeline project?


Q2. Along which expressway was the pipeline laid within a narrow utility strip?


Q3. Which national framework does the project exemplify in practice?


Q4. Which engineering technique was used to cross difficult terrain in the Western Ghats?


Q5. What is the gas carrying capacity of the Mumbai–Nagpur pipeline?


Your Score: 0

Current Affairs PDF January 21

Descriptive CA PDF

One-Liner CA PDF

MCQ CA PDF​

CA PDF Tamil

Descriptive CA PDF Tamil

One-Liner CA PDF Tamil

MCQ CA PDF Tamil

CA PDF Hindi

Descriptive CA PDF Hindi

One-Liner CA PDF Hindi

MCQ CA PDF Hindi

News of the Day

Premium

National Tribal Health Conclave 2025: Advancing Inclusive Healthcare for Tribal India
New Client Special Offer

20% Off

Aenean leo ligulaconsequat vitae, eleifend acer neque sed ipsum. Nam quam nunc, blandit vel, tempus.